Notification of major gas works on North Street, Chichester

By April 24, 2019City News

A forthcoming upgrade of the gas network in North Street, Chichester involves the essential replacement of old metal gas mains with a new plastic pipe. We’ve been informed that this work will ensure a safe and reliable gas supply to the local area.

The work will start on 29 April 2019 until 13 May 2019

To ensure everyone’s safety around the work area, the work will involve a temporary road closure and traffic lights, including the following:

  • North Walls will be closed at the junction of North Street to just above number 25 North walls.
  • Two-way traffic lights will be in place along North Street, these lights will be manually operated to minimise the disruption.

The work will take place Monday to Friday between 7.30am and 6pm and Saturdays if required, however we have been assured that they will try to minimise noisy activities where possible.

If you have any questions or concerns, please contact us on [email protected].